Payment cycle worked worksheet

Practise a complete payment cycle with a cumulative valuation, retention, prior assessment and receipt reconciliation.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Complete the working sheet using your own cycle. Separate the current amount applied for from the assessed amount and the cash received.

Payment cycle worked worksheet

Complete the working sheet using your own cycle. Separate the current amount applied for from the assessed amount and the cash received.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Payment cycle worked worksheet

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payment cycle worked worksheet: completed fictional example
CycleGross cumulative (£)Retention (£)Previous assessed (£)Current application (£)Current assessed (£)Cash received (£)Assessed balance (£)
October£120,000.00£6,000.00£90,000.00£24,000.00£22,000.00£20,000.00£2,000.00

Example amounts exclude VAT. The £24,000 application, £22,000 assessment and £20,000 receipt are different stages; the assessment difference remains unresolved.

Understanding your results

Example amounts exclude VAT. The £24,000 application, £22,000 assessment and £20,000 receipt are different stages; the assessment difference remains unresolved.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.