Payment application template

Prepare a cumulative interim valuation showing work, changes, retention, prior assessments and the current amount requested.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Measure at the agreed valuation date. Use the contract valuation and retention rules, then reconcile the current application to earlier assessments.

Payment application template

Measure at the agreed valuation date. Use the contract valuation and retention rules, then reconcile the current application to earlier assessments.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Valuation detail

Scroll across if needed to read the whole record. A dash means no value has been entered.

Valuation detail: completed fictional example
ItemDescriptionCumulative value (£)Supporting record
MW-01Measured original work£110,000.00Measure MW-10; drawing P-104 C
CH-08Agreed additional work£10,000.00Change agreement A-08

Application summary

Scroll across if needed to read the whole record. A dash means no value has been entered.

Application summary: completed fictional example
Cycle / valuation dateGross cumulative (£)Retention (£)Previous assessed (£)Current application (£)VAT / payment basis
October / 20 Oct 2026£120,000.00£6,000.00£90,000.00£24,000.00Excluding VAT; check invoice and tax treatment separately

Example retention is £6,000 on £120,000. Previous assessed payments of £90,000 are not the same as cash received. Review the separate cash reconciliation before chasing payment.

Understanding your results

Example retention is £6,000 on £120,000. Previous assessed payments of £90,000 are not the same as cash received. Review the separate cash reconciliation before chasing payment.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.