Variation register template

Follow each change from instruction through notice, valuation and payment application without losing its supporting records.

by Jack Butler-Kettle · About 3 min readShare

How to use it

Give each change a stable reference. Keep the instruction, required notices, valuation and application reference together.

A register records what happened. It does not turn an unauthorised instruction into an entitlement or replace notice requirements in your contract.

Variation register

Keep stable references from instruction through valuation and application. Amounts exclude VAT.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Variation register

Scroll across if needed to read the whole record. A dash means no value has been entered.

Variation register: completed fictional example
Variation refChange descriptionInstruction / date / authorityNotice / date / service proofValuation evidenceClaimed value (£)Assessed value (£)Difference (£)Application ref / dateStatus / next action
V-001Additional partitions, Level 2SI-17 / 2026-09-01 / authority checkedN-17 / 2026-09-02 / receipt retainedDrawing rev C; quantities Q17; agreed rates£6,000.00£4,200.00£1,800.00APP-06 / 2026-09-20Request explanation of excluded quantities
V-002Revised door ironmongerySI-19 / 2026-09-05 / authority checkedN-19 / 2026-09-06 / receipt retainedSupplier quotation SQ19; scope comparison£2,500.00£2,500.00£0.00APP-06 / 2026-09-20Valuation agreed; trace payment separately

Leave an absent assessment blank. This is a record, not a contractual notice. Reconcile actual payments separately.

Understanding your results

Use the status and value columns to distinguish notified, priced, assessed and agreed changes. Check that instructions and evidence support each item. A register entry does not itself authorise work or establish an agreed valuation.

How it works

  • Record what changed, who instructed it and the instruction date. Keep the original drawing, email or site instruction.
  • Check authority, confirmation requirements and notice deadlines against your contract. Record what you actually sent and retain proof of service.
  • Build the valuation from the applicable rates or evidenced cost. Link quantities, daywork sheets and invoices to the same reference.
  • Compare claimed and assessed values at the same date. Leave an absent assessment blank rather than entering an assumed zero.
  • Reconcile each item to the application and payment records. A valuation difference does not show the entire unpaid balance.

The fictional example records £6,000 claimed and £4,200 assessed for additional partitions, leaving a £1,800 valuation difference.

Our Change valuation and compensation-event quotations service maintains the ordinary change record and valuation. An Variation Recovery examines disputed instructions, valuation and payment.