Payment cycle register

Follow an application through the assessment, final payment date and cash received without confusing those different amounts.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Use one row per cycle. Enter the assessed current payment after checking the notice; reconcile each receipt to the bank record.

Payment cycle register

Use one row per cycle. Enter the assessed current payment after checking the notice; reconcile each receipt to the bank record.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Payment cycle register

Scroll across if needed to read the whole record. A dash means no value has been entered.

Payment cycle register: completed fictional example
CycleApplication (£)Assessed current payment (£)Final payment dateReceived (£)Assessed balance (£)Evidence / action
September£24,000.00£22,000.0016 Oct 2026£20,000.00£2,000.00Application APP-09; notice PN-09; bank B-17; chase £2,000
October£18,000.00–16 Nov 2026£0.00–Application APP-10 in draft; assessment not yet received

An unassessed amount remains blank. An assessed balance is not a conclusion about the correct notified sum or contractual entitlement.

Understanding your results

An unassessed amount remains blank. An assessed balance is not a conclusion about the correct notified sum or contractual entitlement.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.