One folder per cycle holds the application as sent, every notice received, the receipts, the follow-up emails and a log of the dates. When a question comes up 2 years later, the answer is in one place.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
A payment question 2 years on is answered by documents, not memory. The documents are spread across an email account, a shared drive, a portal and a phone. Usually someone who was not there has to find the application as sent and prove the date. They have to find the notice, or prove there was none, and find the receipts. If each of those is a search, the answer takes days and comes with gaps. If each cycle has one dated folder holding everything that went out and came in, the answer takes 10 minutes. It comes with a complete file an adjudicator can read.
How do I do it?
- Create a folder for each cycle at the start of the job, numbered and dated, before the first application goes.
- Save into it the application as sent, the sent email with its recipient list, the delivery and read receipts and the portal confirmation.
- Save every payment notice and pay less notice as received, with the email it came in, the day it arrives.
- Keep a one page log at the top of the folder listing each document and the date it went out or came in.
- Add the follow-up emails, call notes and remittance advice as they arrive.
- Close the folder when the cycle is paid.
Our Payment applications and valuations organises each application, notice and receipt as one retrievable payment-cycle record.