Skip to content

Name documents so a stranger could follow them

Name every file by project, document type, cycle number and date. It feels fussy until someone who isn't you, a colleague, a lawyer or an adjudicator, has to rebuild what happened from your files.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A file called final v3 revised means something to the person who saved it, on the day, and nothing to anyone else. When a dispute is being prepared, your files are read by a colleague who was not on the job, an adviser or an adjudicator. Each has to work out what every document is before they can use it. Every minute spent decoding file names is a minute not spent on the case. And a document nobody can identify for certain is a document nobody can rely on. A naming rule costs nothing to follow and removes the problem.

How do I do it?

  1. Agree one naming pattern for the company: project code, document type, cycle number, date, in that order.
  2. Pin the pattern up where applications are prepared, and save a copy in the file server's top folder.
  3. Name every document when you save it, including incoming notices, which arrive with the sender's file names.
  4. Use the date and a revision letter in a file name, never words like final, latest or revised.
  5. Spot check a cycle folder each month and rename anything that has slipped.

Our Payment applications and valuations establishes file naming that connects each document to its contract, cycle and version.

Browse payment and deductions in the Library

Browse the Library