Skip to content

How long does construction adjudication take?

Usually 28 days from the referral to the decision, or up to 42 if the referring party agrees, so about 5 to 8 weeks in all.

Updated: . By Jack Butler-Kettle, Construction Claims Consultant.

If a referral has already landed, see how to map the 28 days from the actual documents.

The answer

Section 108 of the Housing Grants, Construction and Regeneration Act 1996 sets a short, fixed timetable. You serve a notice of adjudication. The adjudicator is appointed, and the referral goes to them, within 7 days of that notice. The adjudicator must then decide within 28 days of the referral. You, as the referring party, can agree to extend that by up to 14 days. It can go longer only if both sides agree. Our adjudication timetable counts these dates from your notice. Inside the 28 days the adjudicator sets deadlines for the response, a reply and sometimes a further reply, often a week apart, and may hold a meeting. If the losing side does not pay, enforcing the decision in court is a separate step that usually takes several more weeks. The real time goes into preparation before the notice. A referral that arrives with its documents and figures in order is decided on them. A response built from scratch inside a 7-day deadline rarely is.

Example

Illustrative example. The scenario and figures are invented.

The facts

You serve a notice of adjudication over an underpayment on 1 September, and the referral follows on 5 September. You need to know when the decision is due and how long your main contractor has to answer.

What happens

  1. The decision is due by 3 October, or by 17 October if you, as the referring party, agree the extension.
  2. A response deadline of 19 September gives your main contractor 2 weeks to answer.
  3. Your subcontract, application, notices, records and figures go in complete with the referral, because your reply can only deal with what the response raises.

The timetable

StepDate
Notice of adjudication1 September
Referral5 September
Response deadline19 September
Decision due3 October
Decision due if the referring party agrees the extension17 October

The outcome

The decision is due by 3 October, or 17 October with your agreement. Your case has to be ready before the referral goes in on 5 September.

Underpayment Claim builds the documents and the figures before the clock starts.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 108 (Right to refer disputes to adjudication). legislation.gov.uk.