Skip to content

What does the Price for Work Done to Date mean under NEC4 Options A and B?

Under Option A it is the Prices of completed activities; under Option B it is measured quantities at bill rates, plus the completed share of lump sums.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare

The answer

For your NEC contract, verify the selected option, definition and amendments against your own activity schedule or bill. The main-contract pricing document does not set your entitlement.

Under Option A it is the total of the Prices for each group of completed activities and each completed activity not in a group. An activity is completed only when it has no Defects that would delay, or be covered by, the work that immediately follows. There is no payment for an activity that is partly done, however nearly. So the activity schedule is your cash flow. Large activities mean long gaps between payments, and the relevant completion test concerns Defects that would delay or be covered by immediately following work; not every minor Defect necessarily prevents payment.

Under Option B it is the quantity of work completed for each item in the Bill of Quantities, times the rate for that item. Add the completed proportion of the work covered by each lump sum item. Option B is remeasured, so you are paid for the quantity done, not the quantity billed.

Plant and Materials delivered but not yet built in are not part of the Price for Work Done to Date under either option. The exception is where the activity schedule or the bill provides for them. That surprises Contractors used to other forms.

Implemented compensation events change the Prices, through the activity schedule under Option A and the bill under Option B. Track how implemented changes alter the Prices, and check the actual assessment and implementation provisions before including a pending event.

Four mistakes are common. Option A applications claim percentages of activities, or activities that still carry Defects. The activity schedule is never updated for compensation events. Option B applications are measured against bill quantities, not the site. And lump sum proportions are claimed with no basis.

Use the definitions in your actual NEC4 Engineering and Construction Subcontract, including amendments, rather than assuming every ECC provision is identical. Has the payer paid nil against an activity, or a quantity below your measure? Then check its assessment against the activity schedule or the bill before you accept the figure.

Our Payment applications and valuations applies the relevant activity or measurement basis while keeping other adjustments visible.

Browse payment and deductions in the Library

Browse the Library