Skip to content

How do JCT Pay Less Notices and Payment Notices work?

Under JCT the Interim Certificate is the Payment Notice, and a Pay Less Notice in time is the only way to pay less than the notified sum.

Updated: . By Jack Butler-Kettle, Construction Claims Consultant.

The answer

If no certificate is issued in time, the Contractor's Interim Payment Notice stands in. This follows the Housing Grants, Construction and Regeneration Act 1996. Section 110A requires a Payment Notice stating the sum considered due and how it was worked out. Section 110B lets the payee give its own notice when the payer's is not given. Section 111 requires the notified sum to be paid by the final date for payment, unless a Pay Less Notice is given in time. In the JCT Standard Building Contract With Quantities 2016 (SBC/Q), the interim payment rules are in section 4. The Architect/Contract Administrator's Interim Certificate, issued no later than 5 days after the due date, is the Payment Notice. If no certificate is issued in that time, the Contractor's interim payment application, if it made one, becomes its Interim Payment Notice. If it made none, it can give an Interim Payment Notice at any time after that period. The final date for payment then moves back to reflect how late it was given. The Employer, or someone it authorises, gives any Pay Less Notice no later than 5 days before the final date for payment. It must state the sum the Employer considers due at the date of the notice and how that was worked out. Three things go wrong again and again. An Interim Certificate is issued late and treated as if it still fixed the sum. A Pay Less Notice arrives before the final date but outside its own window. Or a certificate gives a figure with no basis, which invites a challenge to the notice rather than to the valuation. The JCT sub-contracts follow the same pattern one tier down. Your main contractor gives the Payment Notice and any Pay Less Notice to you, so check the dates in your own sub-contract, not the main contract.

Example

Illustrative example. The scenario and figures are invented.

The facts

The Interim Valuation Date is the 10th of a 30-day month. So the due date is the 17th, and the final date for payment is the 1st of the following month. The Contractor applies for £180,000 on the 10th. The Employer thinks £160,000 is due.

What happens

  1. No Interim Certificate is issued by the 22nd.
  2. The Contractor's application becomes its Interim Payment Notice, and £180,000 is the notified sum.
  3. To pay £160,000, the Employer must give a Pay Less Notice by the 26th stating £160,000 and how it was worked out. If it does, it pays £160,000 on the 1st.
  4. Say instead the Architect/Contract Administrator issues a late Interim Certificate for £160,000 on the 28th, and the Employer pays that. It is neither the Payment Notice for the cycle nor a Pay Less Notice in time.

The cycle in figures

ItemAmount
Application, and Interim Payment Notice£180,000
Sum the Employer considers due£160,000
Shortfall without a Pay Less Notice in time£20,000

The outcome

With a Pay Less Notice in time, the Employer pays £160,000. Without one, the £20,000 short of the £180,000 notified sum is a notified sum left unpaid, whatever the work was worth.

To have your main contractor's notices tested against the dates in your sub-contract, see our Underpayment Claim service.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, Part II (Construction contracts), as amended by the Local Democracy, Economic Development and Construction Act 2009, Part 8. legislation.gov.uk.
  2. Housing Grants, Construction and Regeneration Act 1996, s 110A (Payment notices: contractual requirements). legislation.gov.uk.
  3. Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice). legislation.gov.uk.
  4. Housing Grants, Construction and Regeneration Act 1996, s 111 (Requirement to pay notified sum). legislation.gov.uk.