Keep the exact files and covering message actually issued, separate from the working spreadsheet. A PDF copy helps preserve the appearance, but retain an issued spreadsheet too if that was part of the required submission.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
The spreadsheet you build the application in keeps changing. It is rolled forward next month, corrected when a measure is revised and reformatted when someone tidies it. After 6 months it no longer shows what the payer received on any given date. Nobody can reliably say which version they got. That matters the day the payer says the application it received left out an item, or showed a different sum. Keep an unchanged copy of every issued file in the cycle folder, together with the email or portal record. A PDF snapshot is useful, but must not replace the original issued spreadsheet or attachments.
How do I do it?
- Print the finished application to PDF, with the date and cycle number in the file name.
- Send the format the contract requires, including the spreadsheet where required. Preserve those exact files beside the sent email or portal receipt.
- Keep the working spreadsheet in a separate working folder and roll it forward from there.
- Never overwrite issued files. Save any properly submitted revision as a new dated version, with its own service record.
Our Payment applications and valuations preserves the issued version and its attachments separately from working calculations.