For a payment governed by the Construction Act, the notified sum comes from the valid notice that applies to that cycle. An application only sets it where the contractual or statutory requirements are met.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
For a payment governed by the Housing Grants, Construction and Regeneration Act 1996, the notified sum comes from the valid notice that applies to that cycle. An application only sets it where the contractual or statutory requirements are met.
A valid payment notice sent in time fixes it. If none is sent and your contract makes your application the default notice, your application fixes it. Under section 111 of the Housing Grants, Construction and Regeneration Act 1996, the payer must pay the notified sum by the final date for payment. The exception is a valid pay less notice, sent in time, stating a lower sum. Then the lower sum is what must be paid.
The notified sum is not a valuation of the work. It comes from the notices. That is why a main contractor that misses both notices can owe your full application, whatever the work was worth. What the work is really worth is a separate question, settled separately.
Our Payment applications and valuations keeps the application, assessed valuation, notified sum and actual payment distinct in the cycle record. For a contested position: Underpayment recovery reads your past cycles for sums that fell due and were never paid.