Track every contract's cycles in one place

Track each application, notice, due date and payment in one place. Check which valid document establishes the notified sum instead of assuming silence always makes the application payable.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

On any one job, a missing notice looks like an ordinary delay. Across six jobs, with documents going out and payments coming in on different days, a silent cycle is easy to lose. That silence may mean the sum applied for becomes the sum due under section 110B of the Housing Grants, Construction and Regeneration Act 1996. But that only helps if someone notices before the cycle is paid short and the moment has passed. One tracker across every live contract, updated the day something goes out or comes in, makes a quiet miss stand out. It is also the first thing any adviser will ask to see.

How do I do it?

  1. Build one sheet with a row per cycle for every contract. Record the dates and sums of the application, the payment notice, any pay less notice and the payment, and the final date for payment.
  2. Keep the sheet where the whole commercial team can see it, not in one person's inbox.
  3. Update the row the day a document goes out or comes in, not at month end.
  4. Colour any cycle where the payment notice deadline has passed with no notice, and any final date for payment passed with no payment.
  5. Act on urgent notice and payment issues as they arise; use a Monday review as an additional check, without waiting past an earlier deadline.

Our Payment applications and valuations gives each live cycle a recorded owner, next action and evidence reference.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice). legislation.gov.uk.