Builder stage payment schedule

Connect each proposed stage payment to a measurable milestone, evidence, assessment and actual receipt.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Agree objective completion evidence and payment terms before work starts. Record whether a stage is complete rather than paying solely because its forecast date has arrived.

Builder stage payment schedule

Agree objective completion evidence and payment terms before work starts. Record whether a stage is complete rather than paying solely because its forecast date has arrived.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Builder stage payment schedule

Scroll across if needed to read the whole record. A dash means no value has been entered.

Builder stage payment schedule: completed fictional example
Stage / triggerStage amount (£)Assessed (£)Paid (£)Assessed balance (£)Evidence / dateStatus
Foundations complete£15,000.00£15,000.00£15,000.00£0.00Inspection record F-01; 30 SepComplete and paid
Structure watertight£25,000.00£20,000.00£10,000.00£10,000.00Inspection S-01; roof detail outstandingPart assessed; clarify remaining scope
Practical completion£10,000.00–£0.00–Completion evidence not yet availableNot yet assessed

Example amounts exclude VAT. A stage amount is not automatically payable in full where the agreed trigger has not occurred. Apply the actual contract payment process.

Understanding your results

Example amounts exclude VAT. A stage amount is not automatically payable in full where the agreed trigger has not occurred. Apply the actual contract payment process.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.

If you need help preparing or reviewing the project records, our quantity surveying services explain the tasks available under a separate appointment. Agree the deliverable, responsibilities and required specialist input before work starts.