Check the contract permits how you're sending it

If you serve by email, make sure the contract allows it. Turn on delivery and read receipts and keep them, because when a dispute turns on whether something arrived, a receipt beats any memory.

Updated: . By Jack Butler-Kettle, Construction Claims Consultant.

Why it matters

Sending a document and serving it are different things, and the contract decides whether it was served. Say the contract requires post or hand delivery to a named address, and the application went by email. Your main contractor can argue the cycle never started. Even where email is allowed, a dispute can turn on whether the application arrived. Then you have to prove it. Remembering that it went at about 4pm does not do that. A delivery receipt and a read receipt, saved the same day, do. They cost nothing to collect.

How to do it

  1. Read the notices clause and note which ways of serving documents it allows, and the address or portal for each.
  2. Send by an allowed method as well whenever email is not allowed, and keep the proof of posting or the signed delivery note.
  3. Switch on delivery and read receipts in your email for every application and notice you send.
  4. Save each receipt into the cycle folder beside the sent application on the day it comes back.
  5. Screenshot the portal's confirmation, with its timestamp, wherever the contract allows a portal, and file that too.

Example

Illustrative example. The scenario and figures are invented.

The facts

A subcontract allows service by email to a named address and by recorded post. The subcontractor's application seven, for £64,000, goes by email on the 28th. No Payment Notice or Pay Less Notice arrives. The main contractor later says the email was never received.

What happens

  1. The subcontractor's QS finds the delivery receipt showing the email reached the main contractor's server at 10:42 on the 28th.
  2. The read receipt shows the named recipient opened it at 11:15 the same morning.
  3. The QS sends both receipts to the main contractor with the sent item and the demand for payment.
  4. The main contractor drops the point and pays the sum applied for by the final date for payment.

The outcome

The £64,000 is paid in full without adjudication. Two receipts that took a minute to save answered the question of whether it arrived.