Final account reconciliation template

Compare the two final account positions line by line and separate valuation disagreements from payment still outstanding.

by Jack Butler-Kettle · About 3 min readShare

How to use it

Put both parties' figures on the same basis and at the same valuation date. Keep disputed items separate from agreed sums.

The difference between valuations is not automatically the amount payable. Reconcile payments received, retention, tax and any other adjustments separately.

Final account reconciliation

Compare the same valuation date and scope. Enter omissions and deductions as negative figures. Amounts exclude VAT.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Final account reconciliation

Scroll across if needed to read the whole record. A dash means no value has been entered.

Final account reconciliation: completed fictional example
Item refAccount itemYour valuation (£)Contractor valuation (£)Difference (£)Evidence / valuation basisAgreed / disputedRequired response / next action
BASEOriginal subcontract works£100,000.00£100,000.00£0.00Signed subcontract and scopeAgreedConfirm common valuation basis
VAR-01Instructed variations£25,000.00£18,000.00£7,000.00Variation register and instructionsDisputedReconcile disputed quantities and rates
LE-01Additional evidenced cost£8,000.00£3,000.00£5,000.00Separate cost schedule and event recordsDisputedRequest itemised assessment
CC-01Contra-charge deduction-£3,000.00-£5,000.00£2,000.00Scott schedule and supporting recordsDisputedResolve the £2,000 difference

This compares valuations. Reconcile receipts, retention and tax separately before stating an amount payable.

Understanding your results

Use the differences to identify which items are agreed, disputed or awaiting information. Reconcile the closing balance with payments and retention. A balanced spreadsheet does not mean the other party has agreed the account.

How it works

  • Start with the original contract sum and agreed scope. Record omissions and deductions as negative amounts on both sides.
  • Add variations and other claims using the same references as your applications. Enter a genuine zero where a party rejects an item.
  • Link each difference to its instruction, valuation basis and evidence. Record the specific response needed to resolve it.
  • Check final account deadlines and any wording that could make an assessment conclusive. A spreadsheet does not preserve a missed contractual right.

The fictional account compares £130,000 with £116,000, producing a £14,000 valuation difference. Payments and retention require a separate reconciliation before identifying a payment claim.

For the covering correspondence, use the existing final account dispute letter guidance.

our Final account preparation and assessment service can use the reconciliation to prepare and agree an ordinary closing account. A Final account dispute assessment and response examines items that remain contested and the route to pursuing the balance.