Close the account while the people are still there

Prepare and submit your final account within the contractual timetable while the project team and records are accessible. Respond promptly and keep track of any separate challenge deadline.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

The site manager who remembers why the instruction was given leaves a month after handover. The other side's surveyor who agreed the remeasure in principle moves to another job. After 6 months, two people who were not there are arguing the account from files they did not build. The side that has to prove its case suffers most, and that is usually the one claiming money. Delay also suits the other party for a simpler reason: money not yet paid is money in its bank. Speed is not aggression. It is the only way to argue the account while it can still be proved.

How do I do it?

  1. Submit the final account within the contract's period, or within a month of practical completion if it sets none.
  2. Take short signed notes from the site team on every disputed item before people leave, and file them with the account.
  3. Answer every query from the other side within a week, and chase every unanswered point of your own on a fixed cycle.
  4. Ask for a meeting date when you submit, and propose the agenda head by head.
  5. Keep a log of the other side's response times; it becomes useful when the account is later said to be unproven.