Skip to content

Diarise the final certificate's conclusive evidence period

Diarise the challenge period the day the final certificate arrives, because many standard forms make it conclusive if nobody starts proceedings in time. It can fix quality or the account, and rights that survived the whole job can lapse in the last weeks through nothing but silence.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

The final certificate arrives when the job is over, the team has moved on and the account feels finished. It can be the most dangerous document in the contract. If the form makes it conclusive unless proceedings start within a set period, a claim argued for a year can close in weeks. All it takes is the period passing unnoticed. Nobody writes to warn you. The habit is mechanical. The day the certificate lands, read the period from the contract, diarise the end date with a warning well before it, and tell your solicitor.

How do I do it?

  1. Read the contract's conclusive evidence clause the day the final certificate arrives, and note what becomes conclusive and when.
  2. Calculate from the trigger the actual clause specifies, checking service and day-count rules. Set reminders that fit the period, which may be shorter than three weeks, and escalate immediately where time is tight.
  3. Tell your solicitor the same day, with the certificate and the calculation attached.
  4. Decide, in writing, whether any head of the account needs proceedings started before the period ends.
  5. Instruct your solicitor with time to spare if it does, not on the last day.

Our Final account dispute assessment and response records final-certificate triggers and escalation dates; urgent questions about preserving rights may need a solicitor.

For what such a clause can make binding, see what a conclusive evidence clause is.

Browse completion and contract endings in the Library

Browse the Library