Build the timeline from your actual JCT contract: application, valuation, due date, payment notice, pay less notice deadline and final date are separate events.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare
The answer
Build the timeline from your actual JCT contract: application, valuation, due date, payment notice, pay less notice deadline and final date are separate events. Read the selected form, edition, particulars, amendments and incorporated payment schedule together.
Which contract terms set the timeline?
JCT's explanation of interim payments illustrates a main-contract mechanism. It is useful context, but does not establish the periods or sender under your contract. Identify your payer and the person responsible for notices. Record the clause and trigger behind each date rather than copying its client's payment calendar.
Which dates need to be recorded?
Check the permitted application window, valuation date, due-date formula, notice deadline and final date. Apply the agreement's day-count and service provisions.
What happens if an application or notice is missing?
A late or missing payer notice does not simply shift the whole calendar: establish whether your compliant application supplies the notified sum or a further default notice is required, and whether that postpones the final date.
Record pay less notices separately from payment notices and valuation disputes. If work continues beyond the last listed payment cycle, verify the continuing mechanism; an extended programme does not automatically extend an exhaustive schedule. Final-payment provisions may also differ from interim ones. Use the calculator only after the actual periods and assumptions are established.
How do you check one payment cycle?
Gather the signed payment provisions, amendments, application and notices for the same cycle. Write down the valuation date, due date and final date for payment separately.
Use the payment dates calculator with the periods that actually apply. Check service requirements alongside the dates. The calculation does not decide whether the content or service of a notice was valid.
Example
The facts
This subcontractor example expressly assumes a signed JCT subcontract with a valuation date of 1 June 2026, a due date seven calendar days later, a final date 21 calendar days after due date, and a pay less notice period of seven days.
What happens
On those assumed provisions, the due date is 8 June and the final date is 29 June. A payer notice required by five days after due date has a deadline of 13 June.
The pay less notice deadline is 22 June. These dates are checked against the actual service and day-count rules; no relevant excluded holiday affects this example.
The subcontractor records the submitted application and notices against that calendar, then separately checks the documents' validity.
What this shows
The example explains how to calculate from verified subcontract terms. Its periods are assumptions, not a timetable for every JCT form.
For when the money must actually arrive under any contract, see how to find the final date for payment.
Our Construction contract management derives the working payment calendar from the signed JCT form and amendments.
Sources
- JCT Explains…Interim Payments (16 October 2023). The Joint Contracts Tribunal.