How do I find the final date for a construction payment?

Check the final date in your contract first. If the relevant Scheme for England and Wales supplies this provision, its period is 17 days from the due date; do not assume every contract uses it.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare

The answer

The final date for payment is the last day the payer can pay without being late. It is counted from the due date, not from your application or your invoice. For a Scheme final balance, the due-date rule is separate from the interim instalment rule shown below; see Scheme for Construction Contracts (England and Wales) Regulations 1998, Part II paragraph 5.

So first find the due date, and what triggers it, in your signed contract and its amendments. Keep four dates apart: the valuation date, the application date, the due date and the final date for payment. Interim and final payments can have different periods, and the rules on serving notices can affect the count.

Where the in-scope contract lacks the required compliant provision, the relevant Scheme provision supplies the gap. Paragraph 8 of Part II of the Scheme for Construction Contracts (England and Wales) Regulations 1998 sets it at 17 days after the due date. That is a fallback for particular cases in England and Wales, not a rule for every payment or every part of the UK.

One possible adjustment is postponement following a later payee default notice. That arises when the payer sends no payment notice. Section 110B of the Housing Grants, Construction and Regeneration Act 1996 can then push the final date back by the days your notice was late. A later invoice does not, as a rule, change it.

Work out every final date for the job the day you sign, and check the contract before you rely on a default.

Relevant England and Wales Scheme interim instalment defaults

Scroll across to read all columns.

Relevant England and Wales Scheme interim instalment defaults
StepScheme default
Due DateThe later of 7 days after the end of the payment period and the payee making its claim
Payment noticeWithin 5 days of the Due Date
Pay less noticeAt least 7 days before the Final Date For Payment
Final Date For Payment17 days from the Due Date

Our Construction contract management records the due date, applicable period and final date separately for each payment cycle.

Sources

  1. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 5 (Final payment balance). legislation.gov.uk.
  2. Scheme for Construction Contracts (England and Wales) Regulations 1998, SI 1998/649, Schedule, Part II, para 8 (Final date for payment). legislation.gov.uk.
  3. Housing Grants, Construction and Regeneration Act 1996, s 110B (Payment notices: payee’s notice in default of payer’s notice). legislation.gov.uk.