Can I suspend work for non-payment?

Potentially, where the Act applies and the section 111 payment obligation remains unpaid after the final date, including a reduced sum after a valid pay less notice. Give at least seven days' compliant notice.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

Potentially, where the Act applies and the section 111 payment obligation remains unpaid after the final date, including a reduced sum after a valid pay less notice. Give at least seven days' compliant notice specifying the grounds and take advice on any uncertainty before stopping.

The right comes from section 112 of the Housing Grants, Construction and Regeneration Act 1996. It applies when a sum due is not paid in full by the final date for payment. You must first give at least 7 days' written notice of your intention, stating the ground. Our payment dates calculator shows the earliest date for one payment cycle.

Before you serve anything, check the payment terms, the sum actually due, the final date and the notices. Check the proof of sending, whether the Act covers your contract, and the contract wording. Then think through what stopping would do: safety, remobilisation and your other work.

A notice template can organise the information. It cannot decide that suspension is open to you, sensible or lawful, or that you will get your time and costs back. So keep the payment and work records together for your solicitor, and get advice urgently.

If payment is already overdue and you are weighing up stopping work, see what to do before you stop.

Before suspending, Overdue payment recovery checks the notice position and prepares the notice of intention for you to serve.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 112 (Right to suspend performance for non-payment). legislation.gov.uk.

Browse payment and deductions in the Library

Browse the Library