SBC/Q 2016 clause 4.13 is a main-contract suspension provision. If you are working under a subcontract, use your own agreement and any applicable statutory right; the main-contract notice recipients are not automatically yours.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
For an in-scope subcontract, Housing Grants, Construction and Regeneration Act 1996, section 112 can permit suspension of some or all obligations when the section 111 payment obligation has not been satisfied by the final date. Identify the operative notified sum, any valid pay less notice and actual receipts. An unpaid reduced sum can still be relevant; a disputed valuation figure is not automatically the sum on which to suspend.
Give at least seven days' compliant notice of intention, specifying the grounds, and verify the permitted service route and day-count rules. Check the actual contract for any additional contractual route. Do not send a notice only to an architect or client's representative because a main-contract guide names them. The statutory suspension right ceases on full payment of the relevant amount.
Record reasonable suspension and remobilisation costs, mitigation and the actual effect on performance. Section 112 addresses reasonable costs and expenses and relevant time limits; your contract may also have a time or cost procedure to follow. Keep the same cost out of overlapping claims.
Before taking the gang off site, resolve any uncertainty over the payment obligation, coverage, notice and consequences with your adviser. The purpose of the checklist is a supported decision, not an assumption that every overdue application permits a stoppage.
To have the notice of intention to suspend prepared for you to serve, and the suspension costed, see our Overdue payment recovery service.