How to prepare and agree a construction final account
Finishing on site does not close every commercial issue. Completion, defects, retention and the final account can each follow a different contractual timetable.
by Jack Butler-Kettle · About 5 min readShare
Before you start
Gather the contract's closing provisions, completion evidence, latest account, variations, payment history and any proposed settlement.
Identify each closing milestone in your contract and the evidence needed for it. Reconcile the final account item by item. Check what any settlement releases before accepting it.
Step-by-step guide
1. Confirm the completion event and deadlines
Your contract completion may differ from completion of the whole project. Check which event controls defects, retention and delay provisions.
Record outstanding work, certificates, handover requirements and agreed access for rectification. Do not treat a site departure date as a certificate.
Read practical completion for terminology. NEC explains Completion and defects for its ECC form; your contract must be checked separately.
2. Reconcile the final account
Start from the contract price or valuation basis. List agreed changes, disputed changes, other adjustments, previous payments and retention separately.
For each item, show your figure, the other assessment, the difference and the evidence. Distinguish gross entitlement from the net balance requested.
Keep this separate from your internal cost value reconciliation (CVR), which compares the job's value and costs. A forecast margin does not establish what the other party owes.
Check VAT and other accounting treatment with the appropriate adviser. A commercial reconciliation should not silently mix tax-inclusive and tax-exclusive figures.
For a homeowner checking the builder’s final bill, start with the agreed price and add or subtract properly valued changes. Remove replaced allowances.
Compare the resulting account with completion records and the agreed scope. Identify incomplete work and defects separately, with their evidence and the applicable procedure.
For illustration, a £60,000 agreement plus £4,000 of agreed changes gives £64,000. If £55,000 has been paid, the arithmetic balance is £9,000.
That calculation alone does not establish when payment is due or resolve disputed items. Check the final-payment and notice procedure.
Our Final account preparation and assessment service uses this reconciliation to prepare and agree the closing valuation. Where items remain contested, Final account dispute assessment and response examine their basis and the evidence needed to resolve them.
3. Separate retention and payment balances
List each release condition and its evidence, then the applicable payment procedure. An assumed percentage or standard main-contract date may be wrong.
Record defects raised, responsibility disputed, access offered and completion of remedial work. Preserve correspondence about refusals or delays in access.
Do not assume every remaining defect permits withholding all retention. The contract, facts and applicable payment rules need examination.
4. Check the settlement before agreeing
Check whether the proposal settles one item, the whole account or wider liabilities. Identify excluded issues and any continuing obligations.
Record the amount, payment deadline, conditions and parties. Obtain advice on unclear release wording before signing.
A final account submission and a binding settlement are different events. This is general learning for the UK construction industry. Check your governing law, contract form and amendments. Statutory procedures differ across England, Wales, Scotland and Northern Ireland.
Before final payment, reconcile previous payments, retention if agreed, remaining deliverables and any proposed release of claims. A defect does not automatically justify withholding the entire balance.
Reconcile the agreed price, changes and payments before assessing the remaining balance. Keep contested items separate from agreed amounts.
If the issue concerns an increased quotation rather than closing reconciliation, see builder charging more than the quote.
Before you finish: Reconcile the final figure to payments and retention without duplication. Confirm who may approve the settlement and what it releases.
Worked example
The facts
A joinery subcontractor calculates a £48,000 final valuation. They have received £43,000 and record £2,000 retention within the unpaid balance.
What happens
They show the £5,000 overall balance and separate the £2,000 retention from the other £3,000.
They check the retention release conditions and document the remaining valuation disagreement.
They read a proposed settlement to see whether it also releases unresolved defect or delay claims.
What this shows
The reconciliation avoids adding retention twice. The example does not assume all £5,000 is immediately payable.
Completion and handover register
Use one row per milestone or deliverable. Distinguish the forecast date from the actual verified event and retain its supporting record.
Free blank template for your own project. The completed example is shown below. No email address required.
View the completed example
Completed fictional example
Westhaven refurbishment · 14 October 2026 · Version 1.0
Completion and handover register
Scroll across if needed to read the whole record. A dash means no value has been entered.
| Milestone / deliverable | Required evidence | Owner | Forecast | Verified actual | Open condition / next action |
|---|---|---|---|---|---|
| Level 1 handover | Joint inspection and signed area record | Site lead | 12 Oct 2026 | 12 Oct 2026 | Record HR-01 signed; protection passed to contractor |
| O&M information | Approved product data and as-built drawing | Design lead | 16 Oct 2026 | – | Drawing P-104 as-built outstanding |
| Retention first release | Contract trigger and supporting certificate | QS | 30 Oct 2026 | – | Forecast only; check certificate and release terms |
The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.