What is a defects liability period?

It is a contractual period for dealing with defects after completion. The correction process, retention release and wider liability need separate checks.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

A defects liability period is a contractual period for dealing with defects after completion. The correction process, retention release and wider liability need separate checks. JCT forms use rectification terminology; NEC uses its own defects date and correction provisions. Read your exact contract and amendments rather than assuming a universal twelve-month period.

Record what starts the period, which defects you are responsible for, how they are notified and the time allowed for correction. A final list or certificate may have a role, but neither is required in identical terms on every contract. Keep access offers, completed repairs and disputed allegations on the record.

Retention may depend on a separate release event and payment procedure. If release is tied to performance or certification under the main contract, have the condition checked against section 110 of the Housing Grants, Construction and Regeneration Act 1996, where applicable. Upstream payment is a separate issue.

Expiry of the correction period does not automatically end liability for a breach or a defect discovered later. A late list is therefore not, by itself, a reason to disregard every allegation.

For how the JCT Standard Building Contract runs the period clause by clause, see how JCT clause 2.38 works.

Our Construction contract management keeps the relevant dates and defect records aligned with completion and release procedures.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment). legislation.gov.uk.