The defects list is long, most of it belongs to other trades, and our whole retention is being kept against it.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

At the end of the defects period, the second release often waits for a certificate, and the certificate waits for a defects list to be closed. That list may include other trades' work, damage caused after you left, wear rather than defects, or items added after the period ended. Ask for the contractual and payment-notice basis for withholding the particular amount.

Your contract decides what the release waits for: a certificate under the main contract, your own defects being made good, or something else. A later defects list does not automatically remove or establish liability. Check continuing obligations, your own release conditions and whether an upstream certification condition is effective under Housing Grants, Construction and Regeneration Act 1996, section 110.

What do I need to do?

  1. Obtain the current defects list and compare each item with your scope and handover records.
  2. Distinguish your work from other trades, later damage and items whose timing or responsibility is disputed.
  3. Assess and address properly attributable work and record any offer to inspect or remedy.
  4. Compare the supported position with the amount withheld and request an evidenced response on the balance.

To have this done for you, see our Retention recovery and Retention tracking and release process setup services.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment). legislation.gov.uk.

Browse completion and contract endings in the Library

Browse the Library