Skip to content

When is retention released in construction?

Usually in two parts, at practical completion and at the end of the defects period, but your contract sets the events and the dates.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

Usually in two parts, at practical completion and at the end of the defects period, but your contract sets the events and the dates. It decides the split, the events and any certificate or application each release needs. No standard date applies to every job. A release falls due only when its event has actually happened, not when the programme said it would.

So for each job, list what is held, the event each release waits for, and whether it has happened. Keep a forecast date apart from a confirmed event, and a confirmed event apart from money due now. Then ask for each release that has fallen due in your next application, with the evidence attached.

The payer may give a reason for holding it: a missing certificate, the employer's own retention, or a notice. Have your solicitor check what that reason does before you accept it or treat the sum as due.

Our Final account preparation and assessment records the release conditions, milestone evidence and payment process for each contract. For a contested position: For help identifying, assessing and pursuing outstanding retention, see our Retention recovery service.

Browse completion and contract endings in the Library

Browse the Library