Skip to content

Can they hold my retention until the employer releases theirs?

Only if your contract says so in terms the law allows, so check the release wording first.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

Only if your contract says so in terms the law allows, so check the release wording first. Many contracts tie each release to your own works, such as practical completion of the contract works, and never mention the employer. If yours is one of them, the employer's release is not a condition of your contract at all.

Some amended subcontracts do link release to the main contractor being paid or certified under its own contract. The Housing Grants, Construction and Regeneration Act 1996 limits how far that can work. Section 113 makes a term ineffective if it makes your payment depend on the payer being paid by someone else, unless that someone is insolvent. Section 110 also limits making your payment depend on obligations under another contract being carried out.

Whether a particular clause is caught depends on its exact wording, so that is a question for your solicitor.

Meanwhile, keep the release in the normal payment cycle. Ask for it in your application with the trigger document attached, and check the payment notice or pay less notice that answers it.

Our Retention recovery answers that reason with the documents and requests the release in your name.

Sources

  1. Housing Grants, Construction and Regeneration Act 1996, s 113 (Prohibition of conditional payment provisions). legislation.gov.uk.
  2. Housing Grants, Construction and Regeneration Act 1996, s 110 (Dates for payment). legislation.gov.uk.

Browse completion and contract endings in the Library

Browse the Library