Claim evidence pack

Assemble a claim issue statement, dated chronology, evidence index and supported calculation from the same fictional event.

by Jack Butler-Kettle · About 3 min readShare

How to use it

Replace the example with contemporaneous records. Preserve original files and show both supporting and contrary evidence; distinguish assumptions from observed facts.

Claim evidence pack

Replace the example with contemporaneous records. Preserve original files and show both supporting and contrary evidence; distinguish assumptions from observed facts.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Issue and chronology

Scroll across if needed to read the whole record. A dash means no value has been entered.

Issue and chronology: completed fictional example
Date / timeEventEvidenceEffect / limitation
7 Oct 08:00–12:00Level 1 access restricted; four installers plannedD-07; AL-07; TS-0716 planned hours; 8 redeployed elsewhere
8 Oct 08:00–12:00Access restricted until 10:00, then reopenedD-08; AL-08; TS-0816 planned hours; 8 productive after reopening
14 OctClaim reviewed against logs and timesheetsReview CR-1432 claimed hours reduced to 16 supported idle hours

Evidence index

Scroll across if needed to read the whole record. A dash means no value has been entered.

Evidence index: completed fictional example
ReferenceRecord / authorOriginal file locationWhat it showsLimit / check
D-07Site diary, A. Reed, 7 Oct/project/evidence/D-07.pdfAccess closed 08:00–12:00; two people redeployedRead with signed timesheets
D-08Site diary, A. Reed, 8 Oct/project/evidence/D-08.pdfAccess reopened 10:00Contradicts four-hour stoppage for all staff
TS-07/08Approved labour allocations/project/evidence/TS-07-08.xlsxNamed hours by work areaCheck no duplicate recovery
AL-07/08Contractor access logs/project/evidence/AL-07-08.pdfAccess closure and reopening timesDoes not establish contractual liability

Supported labour calculation

Scroll across if needed to read the whole record. A dash means no value has been entered.

Supported labour calculation: completed fictional example
DayInitially claimed hoursRedeployed / productive hoursSupported idle hoursVerified cost / hour (£)Supported cost (£)Basis
7 Oct1688£30.00£240.004 people × 4 h; 2 people × 4 h redeployed
8 Oct1688£30.00£240.004 people × 4 h; 4 people × 2 h productive

All evidence references are fictional teaching exhibits. The example supports £480 of recorded idle labour cost; contractual entitlement and completion delay still require separate assessment.

Understanding your results

All evidence references are fictional teaching exhibits. The example supports £480 of recorded idle labour cost; contractual entitlement and completion delay still require separate assessment.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.