Claim evidence pack
Assemble a claim issue statement, dated chronology, evidence index and supported calculation from the same fictional event.
by Jack Butler-Kettle · About 3 min readShare
How to use it
Replace the example with contemporaneous records. Preserve original files and show both supporting and contrary evidence; distinguish assumptions from observed facts.
Claim evidence pack
Replace the example with contemporaneous records. Preserve original files and show both supporting and contrary evidence; distinguish assumptions from observed facts.
Free blank template for your own project. The completed example is shown below. No email address required.
View the completed example
Completed fictional example
Westhaven refurbishment · 14 October 2026 · Version 1.0
Issue and chronology
Scroll across if needed to read the whole record. A dash means no value has been entered.
| Date / time | Event | Evidence | Effect / limitation |
|---|---|---|---|
| 7 Oct 08:00–12:00 | Level 1 access restricted; four installers planned | D-07; AL-07; TS-07 | 16 planned hours; 8 redeployed elsewhere |
| 8 Oct 08:00–12:00 | Access restricted until 10:00, then reopened | D-08; AL-08; TS-08 | 16 planned hours; 8 productive after reopening |
| 14 Oct | Claim reviewed against logs and timesheets | Review CR-14 | 32 claimed hours reduced to 16 supported idle hours |
Evidence index
Scroll across if needed to read the whole record. A dash means no value has been entered.
| Reference | Record / author | Original file location | What it shows | Limit / check |
|---|---|---|---|---|
| D-07 | Site diary, A. Reed, 7 Oct | /project/evidence/D-07.pdf | Access closed 08:00–12:00; two people redeployed | Read with signed timesheets |
| D-08 | Site diary, A. Reed, 8 Oct | /project/evidence/D-08.pdf | Access reopened 10:00 | Contradicts four-hour stoppage for all staff |
| TS-07/08 | Approved labour allocations | /project/evidence/TS-07-08.xlsx | Named hours by work area | Check no duplicate recovery |
| AL-07/08 | Contractor access logs | /project/evidence/AL-07-08.pdf | Access closure and reopening times | Does not establish contractual liability |
Supported labour calculation
Scroll across if needed to read the whole record. A dash means no value has been entered.
| Day | Initially claimed hours | Redeployed / productive hours | Supported idle hours | Verified cost / hour (£) | Supported cost (£) | Basis |
|---|---|---|---|---|---|---|
| 7 Oct | 16 | 8 | 8 | £30.00 | £240.00 | 4 people × 4 h; 2 people × 4 h redeployed |
| 8 Oct | 16 | 8 | 8 | £30.00 | £240.00 | 4 people × 4 h; 4 people × 2 h productive |
All evidence references are fictional teaching exhibits. The example supports £480 of recorded idle labour cost; contractual entitlement and completion delay still require separate assessment.
Understanding your results
All evidence references are fictional teaching exhibits. The example supports £480 of recorded idle labour cost; contractual entitlement and completion delay still require separate assessment.
How it works
The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.
Read the related guidance for the context and checks behind this template.