Claim review and actions record

Review the event, entitlement, calculation and evidence separately, with unresolved objections and corrective actions visible.

by Jack Butler-Kettle · About 2 min readShare

How to use it

Record both supporting and adverse evidence. Assign an owner and deadline to every unresolved point before submitting or responding to the claim.

Claim review and actions record

Record both supporting and adverse evidence. Assign an owner and deadline to every unresolved point before submitting or responding to the claim.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Claim review and actions record

Scroll across if needed to read the whole record. A dash means no value has been entered.

Claim review and actions record: completed fictional example
Review issueClaim positionEvidence / objectionAction / ownerStatus
Cause and responsibilityAccess restriction caused idle labourLogs confirm closure; contractual allocation still to checkQS to review executed access termsOpen
Quantum32 idle hours originally claimed16 hours were redeployed or productiveReduce supported hours to 16; £480 at £30/hCorrected
Time effectTwo days extension requestedActivity interruption alone does not prove completion effectPlanner to compare programme logic and other causesOpen
ServiceNotice N-01 issued 8 OctReceipt R-008 retainedCommercial lead to check deadline and contentReview pending

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

Understanding your results

The completed example uses fictional people, events and records. Replace it with your own verified information and preserve supporting evidence.

How it works

The workbook provides blank working records. Grey cells calculate from the entered inputs; yellow cells are for your information. The completed example stays on this page.

Read the related guidance for the context and checks behind this template.