Keeping records that explain a construction claim

Useful records let another person follow the event, your obligations and your calculation. A large folder is only helpful when its contents can be understood.

by Jack Butler-Kettle · About 5 min readShare

Before you start

Collect the original agreement, correspondence, site records and financial records. Keep originals separate from the working set.

Keep original records and connect them to the facts they support. Distinguish what happened, what the contract requires and what the figures show. Record uncertainty and contrary evidence as carefully as favourable material.

Step-by-step guide

  1. 1. Preserve and index original records

    Keep emails with attachments, dated drawing revisions, original photographs and exported project-system records. Retain metadata where possible.

    Use working copies for highlighting and calculations. Do not silently edit originals or recreate old notes as if they were written contemporaneously.

    If an explanation is written later, label its date and author. Distinguish recollection from a record made at the time.

  2. 2. Connect the issues, rights, events and figures

    Use a chronology for events, a document index for sources, an issue list for disagreements and a calculation for amounts.

    Give each event and document an identifier. A reader should be able to move from a sentence or figure to the record behind it.

    For a starting set of editable registers and correspondence templates, the free Claim prevention pack includes a guide to using them on a project. Adapt the records to your contract and keep the underlying evidence.

    The SCL Protocol emphasises transparent information and methodology for delay and disruption. The organising approach here is a practical suggestion, not a prescribed legal format.

  3. 3. Test the evidence and identify gaps

  4. 4. Prepare a usable evidence pack

    Choose relevant documents and include an index. Use searchable files, clear names and readable scans instead of sending an unexplained archive.

    Keep access controlled and avoid sharing unrelated personal information. Ask about legal privilege before circulating communications with legal advisers.

    Procedural disclosure and confidentiality rules depend on the forum and jurisdiction. Check the directions that apply to your dispute.

Before you finish: Check that each material assertion can be traced to a source and that contrary evidence, estimates and missing records remain visible.

Worked example

The facts

A flooring subcontractor has 200 photos and a £4,800 claim concerning repeated return visits.

What happens

  1. They group photos by date and area and check them against site diaries.

  2. They connect each return visit to the instruction or access record and the associated labour entry.

  3. They remove a duplicated labour entry and clearly label a visit whose reason remains uncertain.

What this shows

The pack becomes easier to test. Better organisation does not turn an unsupported item into an established entitlement.

Claim evidence pack

Replace the example with contemporaneous records. Preserve original files and show both supporting and contrary evidence; distinguish assumptions from observed facts.

Free blank template for your own project. The completed example is shown below. No email address required.

View the completed example

Completed fictional example

Westhaven refurbishment · 14 October 2026 · Version 1.0

Issue and chronology

Scroll across if needed to read the whole record. A dash means no value has been entered.

Issue and chronology: completed fictional example
Date / timeEventEvidenceEffect / limitation
7 Oct 08:00–12:00Level 1 access restricted; four installers plannedD-07; AL-07; TS-0716 planned hours; 8 redeployed elsewhere
8 Oct 08:00–12:00Access restricted until 10:00, then reopenedD-08; AL-08; TS-0816 planned hours; 8 productive after reopening
14 OctClaim reviewed against logs and timesheetsReview CR-1432 claimed hours reduced to 16 supported idle hours

Evidence index

Scroll across if needed to read the whole record. A dash means no value has been entered.

Evidence index: completed fictional example
ReferenceRecord / authorOriginal file locationWhat it showsLimit / check
D-07Site diary, A. Reed, 7 Oct/project/evidence/D-07.pdfAccess closed 08:00–12:00; two people redeployedRead with signed timesheets
D-08Site diary, A. Reed, 8 Oct/project/evidence/D-08.pdfAccess reopened 10:00Contradicts four-hour stoppage for all staff
TS-07/08Approved labour allocations/project/evidence/TS-07-08.xlsxNamed hours by work areaCheck no duplicate recovery
AL-07/08Contractor access logs/project/evidence/AL-07-08.pdfAccess closure and reopening timesDoes not establish contractual liability

Supported labour calculation

Scroll across if needed to read the whole record. A dash means no value has been entered.

Supported labour calculation: completed fictional example
DayInitially claimed hoursRedeployed / productive hoursSupported idle hoursVerified cost / hour (£)Supported cost (£)Basis
7 Oct1688£30.00£240.004 people × 4 h; 2 people × 4 h redeployed
8 Oct1688£30.00£240.004 people × 4 h; 4 people × 2 h productive

All evidence references are fictional teaching exhibits. The example supports £480 of recorded idle labour cost; contractual entitlement and completion delay still require separate assessment.

Sources

  1. Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.