Skip to content

What counts as contemporaneous evidence on a construction job?

Contemporaneous evidence is any record made at the time something happened, such as a diary entry, a dated photo or an email sent that day.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

On a construction job, that means site diaries, allocation sheets, daywork sheets, delivery tickets, dated photos and meeting minutes. It also means emails and messages sent as things happened. It usually counts for more than a statement written months later, because nobody knew then that a dispute was coming. When the other party makes a claim against you, these are the records an adjudicator will look for.

A record is only as good as its date and its source. So date every entry, name who made it, and keep the original file, not a copy or a screenshot. Never go back and change a record: add a dated note instead. Records written up later can still help, but label them for what they are.

How much weight a record carries is for your solicitor and the adjudicator. Keeping it is a job for your site team, every day.

Our Construction contract management establishes how original records, dates, authors and revisions are retained during the project.

Browse dispute resolution and defence in the Library

Browse the Library