Photograph with context, then detail

Take a wider view before the close-up, and record the date, location and what the image shows. Keep the originals; a photograph alone may not establish timing, cause or responsibility.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A photo proves what is in the frame and nothing else. A close-up of a flooded trench could be any trench, on any job, on any day. Without a wide shot, a date and a named position, the other party can say it shows another area, another week, or a problem you caused. Photos also disappear with the phone they were taken on. The operative leaves, the handset is replaced, and the pictures go with it. A routine walk, filed the same week, turns a heap of images into a dated record of the whole job.

How do I do it?

  1. Set a fixed route of positions round the site, and photograph from each one at the same time every week, wide shot first.
  2. Take the wide shot that places any problem, then the detail, with something in frame that shows scale or location.
  3. Photograph every area as you hand it over, so its condition on the day you left is on file.
  4. Leave the phone's date and location settings on, and never edit or rename the originals.
  5. Upload the week's photos to the project folder by Friday, in a folder named by date and area, with a one-line note on anything unusual.

Our Defects and damage cost defence preserves photographs with dates, locations and links to the work they may later help explain.