An extension of time assesses the effect of qualifying events on the contractual completion date. It is not simply the number of days an activity stopped.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare
The answer
Identify the applicable event and notice requirements, then assemble the programme and progress records. The SCL Delay and Disruption Protocol discusses delay analysis; it is guidance, not the contract. The method must suit the terms, available records and timing of the assessment.
Explain the affected activities, their sequence and their effect on completion. Test available float, mitigation and other causes rather than adding every delay together. Concurrent delay needs particular care.
For illustration, assume a ten-day interruption causes six days of qualifying completion delay after programme analysis, with no competing delay or other adjustment. An accepted six-day extension moves a 10 June completion date to 16 June. This assumed result does not establish entitlement to six days of additional cost. Extension-of-time evidence preparation organises the notices and event records alongside the client's appointed planner. Separate time entitlement from loss and expense.
Sources
- Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.