Prolongation money, the cost of being on site longer, is only as strong as the time case under it. Price it on an old version of the delay analysis, and the other party only has to lay the two side by side.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
Delay analysis and cost assessment must use compatible events, assumptions and versions. An extension of time alone does not establish monetary entitlement. Agree the compensable cause with the representative, use the appointed planner’s analysis where required, and link additional costs to when and why they were incurred. Reconcile overlap, mitigation and amounts already recovered before submitting the figures.
How do I do it?
- Identify the contractual money route and relevant causes with the representative. Obtain the programme specialist's time analysis separately and record the supported cost periods and assumptions.
- Record the version and date of the delay analysis or extension of time behind the claim, and show it on the valuation's front page.
- Ask to be told of every change to the analysis, and revalue the affected periods when one arrives.
- Check every period and event in the claim against the latest version of the analysis before it goes in.
- Say so in the submission if a period has moved and there is no time to revalue it, instead of sending a mismatch.
Our Extension-of-time evidence preparation aligns the financial evidence with the appointed planner's analysis while keeping time and money entitlement distinct.