Have someone check the claim with fresh eyes

Ask a suitable reviewer to follow the claim from event to evidence to amount. Use their questions to find gaps before submission.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare

Why

An independent check can help, especially on a complex or valuable claim. For smaller work, a deliberate second review is still useful. Neither approach replaces specialist advice where it is needed.

How do I do it?

  1. Give the reviewer the contract basis, chronology, calculation and referenced records.
  2. Ask them to trace a sample from each claimed item to its evidence.
  3. Correct errors, explain assumptions and flag unresolved issues before approval.

Our Delay and disruption cost recovery tests whether another reader can follow the claim from event to records to calculation.