Check whether the contract requires actual additional cost, agreed rates or another method. Where actual cost is the basis, show the affected resources and periods with evidence rather than an unexplained percentage.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
Why
An unsupported percentage gives little to test. Contractual rates or percentages can apply where the actual valuation rule provides for them; otherwise explain the supported additional cost. You then have nothing to push back with. A build-up is slow because it is real: which staff, which weeks, which cabins, which plant, at what cost, from which records. Its value is that every line can be checked against a timesheet or an invoice. Each line is easier to review, but an unanswered cost item is not automatically payable.
How do I do it?
- List the site resources actually used in the period: staff by name and role, cabins and welfare, plant, temporary services and insurances.
- Record the weeks each one was on site, from the allocation sheets, hire records and invoices.
- Apply the cost rate from the payroll or invoice to each week, and note the source beside the figure.
- Take out anything already recovered elsewhere in the claim, and anything not caused by the event you are valuing.
- Total the build-up week by week and present it with the records referenced.
Our Delay and disruption cost recovery distinguishes time-related additional preliminaries from fixed costs and sums already allowed elsewhere.