You need records of the event, the work it affected, the resources used and the cost, with each linked to the others.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
Build every cost line from the same set of facts. Record the event and its date, and the location or activity it affected. Record the named person or plant and the period involved. Then add the source document, how the cost was split, the amount and any credit or overlap with other heads.
If an allocation sheet is missing, compare payroll, diaries, access records, instructions and any other evidence you hold. Label anything pieced together later, with who prepared it and on what basis. Keep any cost you cannot yet tie to the event separate from the cost you can support. One missing record does not automatically decide the whole claim.
Make the records traceable
Give each event and cost line a stable reference. Keep an evidence index recording the document date, source, relevant page and what the document supports.
Your cost schedule should link resources, quantities, rates and credits. Preserve original files beside the working schedule. Record which figures remain estimates and why, and distinguish a document that proves cost from one that proves causation.
Building the prolongation cost shows one cost head with its credits and overlap reconciled. Delay and disruption cost recovery brings the explanation, figures and evidence together where you want the claim prepared for you; Delay and disruption records setup sets up the record routine while the project is still running.