Skip to content

What is concurrent delay, and can I still claim time or money?

Concurrent delay concerns competing causes of delay to completion. Overlapping dates alone do not establish it, and entitlement to time and money must be assessed separately.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare

The answer

The SCL Delay and Disruption Protocol distinguishes true concurrent delay from events that merely happen together. Your planner needs to establish the effect of each event on completion, using the relevant programme and progress records. The protocol is guidance, not a substitute for your contract or its governing law. Amendments may expressly allocate concurrent-delay risk.

An extension of time does not automatically carry compensation: identify which additional costs the event you rely on actually caused, separating costs that would have arisen from your own delay.

Give required notices while the analysis is developed. Your representative confirms the contractual position; we organise the records and assess the cost evidence alongside the appointed planner.

For the event records and commercial evidence, use Extension-of-time evidence preparation. For an assessment of the additional costs, see Delay and disruption cost recovery.

Sources

  1. Delay and Disruption Protocol, 2nd edition, February 2017. Society of Construction Law.

Browse delay and disruption in the Library

Browse the Library