Skip to content

What is the difference between JCT Relevant Events and Relevant Matters?

Relevant Events concern extensions of time; Relevant Matters concern loss and expense. An event may qualify under both lists, but the tests and submissions remain separate.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

Use the lists and procedures in your own contract. JCT subcontracts may use the terms Relevant Sub-contract Events and Relevant Sub-contract Matters. Check the form, edition, selected options and amendments rather than borrowing a main-contract clause number.

For time, establish a qualifying event and its effect on completion. For money, establish the relevant contractual basis, notice compliance and resulting additional cost. JCT's explanation of the 2016 provisions illustrates the separate loss-and-expense procedure. The 2024 launch guidance identifies revisions and optional matters; the lists are not identical across editions.

A granted extension is useful evidence of the time position, but does not establish every day or cost claimed. Delay and disruption cost recovery connects the financial assessment to the specific event, records and compensable period. The EOT calculation explanation covers the separate programme question.

Key differences

Scroll across to read all columns.

Relevant Events and Relevant Matters compared
FeatureRelevant EventsRelevant Matters
QuestionIs an extension of time justified?Is loss and expense recoverable?
BasisThe applicable event list and time provisionsThe applicable matter list and financial provisions
EvidenceThe event and its effect on contractual completionThe cause, compensable period, resources and additional costs
ResultA time assessment, not automatic payment for every extended dayA separate financial assessment, not a percentage added to the time award
Contract checkForm, edition, subcontract terminology and amendmentsForm, edition, selected provisions and amendments

Example

The facts

A subcontractor has five days of weather delay and three days affected by an instructed change. Assume their terms allow time for both, but money only for the change.

What happens

  1. The time assessment tests the effect of both events on completion; it does not automatically add their durations.

  2. The cost submission isolates the change-related expenditure and the required notices. They exclude weather costs on the assumed terms.

  3. The subcontractor records the time decision and cost assessment separately, including any amounts already paid in the variation.

What this shows

A single combined claim for eight days of time and money would obscure the different contractual tests. These assumptions are illustrative, not a universal JCT rule.

Sources

  1. JCT Design and Build and JCT Standard Building Contracts 2016: Part II (2017). The Joint Contracts Tribunal.
  2. JCT 2024 In-Person Launch Event presentation (2024), Time Issues. The Joint Contracts Tribunal.

Browse delay and disruption in the Library

Browse the Library