Relevant Events are the causes of delay listed in a JCT contract that can get you an extension of time.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare
The answer
Relevant Events are the causes of delay listed in a JCT contract that can get you an extension of time. JCT subcontracts may use the term Relevant Sub-contract Events; check the terminology and list in your own form and edition. An extension of time moves your completion date, so delay damages are counted from a later date.
Depending on the selected JCT form and edition, the list can include variations and instructions, deferred possession and exceptionally adverse weather. It also covers fire, flood and the other specified perils, strikes, some acts of government and force majeure. Hold-ups and defaults by the employer, or the people it is responsible for, are on it too. In a JCT contract, so are hold-ups and defaults by the other party and the people it is responsible for.
Relevant Events are about time. Relevant Matters are the shorter JCT list about money. So exceptionally bad weather can get you more time, but no money.
A Relevant Event does not move your date on its own. Notify the delay once it becomes reasonably apparent, then send particulars and your estimate of the effect. Use the exact list and conditions in your executed contract, including 2016 or 2024 provisions and amendments. Programme analysis informs the completion effect; contractual entitlement and notices require their own assessment. Our part is getting the notice and the records out in time.
For responsibility, deadlines and evidence around Relevant Event notices, Completion-date and notice tracking setup service.