After a delay notice, provide the particulars and updates your contract requires. Explain how the event affects the relevant completion date.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare
Why
A notice alone may not contain enough information to assess time. Avoid assuming that every day of disruption moves completion by a day; programme logic and other causes can matter.
How do I do it?
- Identify the event, contractual basis and affected work.
- Link its timing to the programme and contemporaneous records.
- Submit the required particulars and updates, seeking a planner’s input where the analysis needs it.