Recalculate the liquidated damages before you argue about the delay

Check the rate, relevant completion date, period, cap and arithmetic behind a delay-damages calculation. Keep that check separate from whether the charge is contractually due.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A damages deduction is usually put together quickly, from the original completion date to the date the whole project finished. Both dates can be wrong for your work. Extensions already granted get left out. Your own completion is taken as the main contract's. Sections handed over early are charged at the full rate. A cap is forgotten. The right sum is the rate your contract states. Apply the contract's actual start and end triggers, including any relevant certificate, completion, take-over or sectional provision. Partial possession does not universally produce an automatic proportional reduction. Apply a cap only to the liabilities it covers. You need no delay expert to find the errors, only the contract, the dates and the extension decisions side by side. It is also the quickest ground to agree on, because it is the other party's own arithmetic.

How do I do it?

  1. Take the rate, the counting rule, any cap and any rule for parts taken over early from your signed contract, not the standard form.
  2. List every extension granted, and work out the completion date as extended.
  3. Fix the date your work was actually completed or taken over, from records made at the time.
  4. Re-run the sum, including any reduction for parts taken over early, and set your figure beside the deduction line by line.

Our Delay damages review and response checks the applicable dates, rate and deductions alongside the time-entitlement position.