Skip to content

They're taking liquidated damages out of my payments

The other party has started deducting a weekly rate for a late finish, and each payment is smaller than the last.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

A line for liquidated damages has appeared on your pay less notice. That is the notice the other party sends when it plans to pay you less than the notified sum. The line is a weekly rate times the weeks since your original completion date, and it grows every cycle. It looks like simple arithmetic, which is why hardly anyone checks it.

But the deduction only stands if every part of it holds up. The rate must be the one your contract states. The weeks must run from your completion date as extended. Check any applicable provision for partial possession or take-over and the scope of any cap. A valid payment notice may already incorporate the deduction; paying below the operative notified sum generally requires a valid pay less notice. Whether your date should have moved further is a separate question. Leave it unchecked and you may pay for weeks that were never due.

What do I need to do?

  1. Read the contractual rate, period, counting rule, cap and required notices.
  2. List extension applications and decisions alongside the relevant completion dates.
  3. Recalculate the deduction on the supported dates and show each difference from the payer's figure.
  4. Obtain programme or legal input where needed, and submit the reasoned financial response through the appropriate route.

To have this done for you, see our Delay damages review and response and Completion-date and notice tracking setup services.

If the charge is the other party's own delay costs, not a weekly rate, see what to do when the other party passes its delay costs down to you.

Browse delay and disruption in the Library

Browse the Library