The other party is passing its delay costs down to me

The client charged the main contractor for a late finish. Now that bill, and its own site costs, have landed on our account.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

What does this mean for me?

Your contract has no damages rate, or the other party says the rate is not the whole story. Your account has come back cut by the damages its client took from it, plus its own extended site costs. The whole project's delay has been put down to you.

Where there is no rate, the other party can claim only the loss your late finish actually caused it. That loss is measured from your completion date as extended, not the project's. It has to prove the loss, and show that your delay caused it rather than its own or another trade's. Where several causes overlap, test causation, the contractual risk allocation and any duplication. A proportional split between trades is not automatic. Accept the charge as it stands and you carry the whole project's delay.

What do I need to do?

  1. Request the breakdown, period and evidence for each damages or site-cost charge.
  2. Compare the charges with your obligations, completion date, extension decisions and delay notices.
  3. Test attribution and overlap rather than assuming an upstream charge can be passed down unchanged.
  4. Use appropriate programme and legal advice to resolve disputed causes and terms, then set out the supported financial response.

To have this done for you, see our Delay damages review and response and Completion-date and notice tracking setup services.

Browse delay and disruption in the Library