What happens if I miss the deadline for a delay notice?

It depends on your contract: where the notice is a condition of an extension, a late one can lose you the extension.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

The effect of a missed delay notice depends on your contract: where the notice is a condition of an extension, a late one can lose you the extension. Where it is only a duty, a late notice may still count, but it weakens your position.

So read the clause itself. Look for words such as condition precedent, or a line saying you are not entitled to an extension unless notice is given. Those point to a bar: no notice, no extension. A plain duty to notify forthwith, meaning without delay, usually does not create a bar. A claimed loss of opportunity to mitigate must be tested against the clause, evidence and legal consequences; lateness does not justify an arbitrary reduction in the extension.

Either way, do not stay silent. Send the notice as soon as you realise, with the particulars, the records and a short explanation of why it is late. Some forms also allow the completion date to be reviewed after completion, whether or not every notice was given, so ask for that review in writing. Whether a missed bar can be avoided, for example where the other party caused the delay itself, is a question for your solicitor.

Keeping every delay notice inside its period is what our Completion-date and notice tracking setup routine is for.