Skip to content

Does a site instruction count as a variation?

It does if it changes your work and comes from someone your contract allows to instruct, whatever the form calls it.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

A site instruction can qualify as a variation if it changes your work and comes from someone your contract allows to instruct, whatever the form calls it.

Many main contractors use a site instruction form for day-to-day directions. Some of those change your work, and some do not. One that adds work, changes a detail, moves an access route or resequences your work is a variation in substance. That holds even if the word variation appears nowhere on it. One that only repeats what your contract already requires is not.

Two checks decide it. First, compare the instruction with the agreed contract scope and allocated obligations, as you would any change. Second, check who signed it, because your contract may name the people who can instruct variations.

If the instruction changes your work, reply in writing the same day. Say you treat it as a variation, give it a variation number and say you will value it. If the person who signed it lacks authority, ask someone who has it to confirm the instruction before you start. A site instruction you never answered is much harder to get paid later.

Our Variation management setup service sets up that same-day reply and a register for every instruction on your job.

Our Variations and compensation events checks the issuer, authority and scope effect before the instruction is included in the change register.

Browse changes and extra costs in the Library

Browse the Library