What is a variation order, and what counts as a variation?

A variation order is the other party's written instruction to change your work, but whether a particular direction qualifies depends on your agreed contract scope and variation provisions.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

The answer

A variation order is the other party's written instruction to change your work, but whether a particular direction qualifies depends on your agreed contract scope and variation provisions. Your contract may call it an instruction or a direction instead. Whatever its name, what matters is what it changes.

A change usually counts as a variation if it alters the work your contract describes, or how, when or where you do it. That covers added or omitted work, a different quality or sequence, changed access and changed working conditions. Your contract decides exactly what counts and who has the authority to instruct it.

So start by comparing what you are now being asked to do with the agreed contract baseline, including accepted qualifications and allocated design obligations. Use the drawings, specification, clarifications, amendments and design duties at the revision your contract names, not a tender drawing on its own. Then check who instructed the change and what route your contract sets for it.

Keep the instruction, the source documents, the quantities affected and any notice or valuation rule together in one file. A change in scope does not on its own prove what you will be paid, or that you get more time. Each of those follows its own route under your contract.

Our Variations and compensation events compares the instruction and revised requirements with the original scope before recording and valuing the change.