Is design development a variation?

Not if it only fills in detail your contract already allowed for, but a revision that changes what you agreed to build can be.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 1 min readShare

The answer

Some design development just adds detail that your contract expected and gave someone the job of completing. Other revisions change the performance, quantity, sequence or conditions, or the work itself. Which side of the line a revision falls on depends on your signed documents, clarifications, design duties and approval process. The label on the drawing does not decide it.

So compare each revision with the scope you agreed, and keep the version it replaced. Note who made the decision, and any notice or valuation route that applies. Do not assume a refinement is free, or that every upgrade gets paid. If the answer is disputed, keep that evidence together before anyone argues about the money.

If revised drawings keep reopening the argument on a live job, see what to do when you are told the change is included in your scope.

Our Variations and compensation events distinguishes development already required by the agreement from a changed contractual requirement.