Identify the named roles and instruction process in your contract. Escalate requests from others for confirmation, while checking any delegated authority and the actual circumstances.

by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 2 min readShare

Why

A site request may come from someone whose authority is unclear. Check the contract, any notified delegation and subsequent confirmation before relying on it for payment. Actual or apparent authority and the parties' conduct can also matter; being unnamed is not a universal answer either way.

Keep who requested the change, what they said and who confirmed it on the same record. If authority is disputed, obtain advice promptly while protecting any notice deadline and checking your obligation to comply.

How do I do it?

  1. List the roles your contract names as able to instruct, on the day it is signed. Add the named people and what each can and cannot authorise.
  2. Give the list to your site team, and tell them to report any request from anyone else, not act on it.
  3. Write the same day to the named person when a request comes from anyone else, asking them to confirm the instruction.
  4. Do not start the changed work until the confirmation arrives, unless the named person agrees in writing that you can.

Our Variations and compensation events records who may instruct changes and how instructions are confirmed before costs build up.