Most contracts only make the other party pay for changes that were properly instructed, so get every instruction on paper. If the work has to start first, confirm the verbal instruction in writing the same day and give them the chance to correct you.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare
Why
Instructions get given in a corridor by someone in a hurry. The work gets done, and your request for payment arrives weeks later. By then the person who gave the instruction has moved on, remembers it differently, or is under pressure to say it was included. With nothing written at the time, it is your word against theirs, just when your negotiating position is weakest.
Most contracts also set a form and a time limit for confirmations. One sent late or in the wrong form may count for nothing. A same-day confirmation preserves your account and gives the recipient a chance to correct it. Its contractual effect depends on the actual confirmation mechanism, authority and timing. Silence is not generally acceptance, and a deadline you choose does not by itself make it so.
How do I do it?
- Tell every foreman and supervisor to pass any instruction given on site to the office the same day.
- Carry the confirmation form your contract requires, on paper or on a phone, so you can send it from site.
- Write the same day to the person who gave the instruction and to the person your contract names, by the route it names. Say what was instructed, by whom and when, and copy the site file.
- State that you treat it as a variation and will price it. Request a prompt reply and any required written instruction, distinguishing your requested response date from any contractual confirmation period. Say the work is going ahead in the meantime.
- Number the confirmation and enter it in your variation register before the work starts. Chase a written instruction if your contract requires one, and chase a reply where the change affects the money. Record whether the confirmation was accepted, disputed or met with silence.
- Keep the changed work separate in your records from day one, so the confirmation has costs behind it. Attach the confirmation email as back-up when you first apply for payment for the work.
Our Variations and compensation events connects verbal instructions to the confirmation and notice procedure required by the contract.