Use the daywork basis incorporated into your contract, including its edition, cost definitions, rates and agreed additions.
by Jack Butler-Kettle, MCIArb, NEC Registered Adjudicator · Last reviewed · About 3 min readShare
The answer
Use the daywork basis incorporated into your contract, including its edition, cost definitions, rates and agreed additions. A RICS or CECA label alone does not settle the rate payable or whether daywork valuation is authorised for this work.
For building work, contracts may refer to a definition of prime cost of daywork and percentage additions in the priced documents. RICS's Valuing change describes that approach. Check the actual incorporated publication, trade and edition, what each cost component includes, and the contract's additions rather than treating a historical guidance document as a current tariff.
For civil engineering work, CECA publishes Schedules of Dayworks Carried Out Incidental to Contract Work, with the third edition published on 11 August 2025. A newer publication does not automatically replace the edition or rates agreed in your contract.
Before submitting a sheet, establish the authorised work, valuation basis, labour/material/plant records and required verification. Apply only the agreed additions and reconcile costs already recovered elsewhere. If the contract leaves the basis unclear, seek a documented agreement rather than choosing a percentage or substituting the other party's rate.
Key differences
Scroll across to read all columns.
| Check | Building daywork basis | CECA daywork basis |
|---|---|---|
| Source | The incorporated prime-cost definition and pricing documents | The incorporated CECA schedule and pricing documents |
| Rates and additions | Check permitted costs and the agreed percentage additions | Check the agreed edition, rates, inclusions and additions |
| Evidence | Authorised work, labour, plant, materials and required verification | Authorised work, labour, plant, materials and required verification |
| Which applies? | Only the basis agreed for the work; a RICS label is not a tariff | A newer schedule does not automatically replace the agreed basis |
Example
The facts
A groundworks subcontractor's daywork clause names the RICS definition for building work, with 110% on labour, 15% on materials and 10% on plant. The main contractor's valuation applies the contractor’s own 60% on labour.
What happens
One day's sheet shows prime costs of £400 for labour, £300 for materials and £250 for plant.
With the subcontract percentages added, the day is worth £1,460: £840 of labour, £345 of materials and £275 of plant.
At 60% on labour, the main contractor's figure for the same day is £1,260.
The subcontractor answers with the daywork clause and the percentages they tendered.
One day's daywork
| Item | Prime cost | With the percentage |
|---|---|---|
| Labour, 110% | £400 | £840 |
| Materials, 15% | £300 | £345 |
| Plant, 10% | £250 | £275 |
| Total | £950 | £1,460 |
What this shows
The day is agreed at £1,460. Across the 12 similar days on the sheets, that recovers £2,400 the lower labour percentage would have cut.
Our Variations and compensation events checks which schedule and additions the agreement incorporates before applying daywork rates.
Sources
- Valuing change. RICS.
- Schedules of Dayworks Carried Out Incidental to Contract Work (third edition, 11 August 2025). Civil Engineering Contractors Association.